Lesson Learned





By: Stein-Petter Slatlem

Report No.

8328

Discipline/Origin

Drilling
No origin

Well

Kjøttkake
35/10-13

Date created

2025/02/20
289 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Mud
No classification

Deepsea Yantai


What happened in Surface section:
Having KCL level at 200 kg/m3 was a success factor to drilling section.

What Was Planned

KCL concentration in WBM while drilling top hole with RMR system.

What Was Learned

Always plan for KCL level at 200 kg/m3. If starting at high concentration from the start, it is easier to maintain throughout the section compared to having to catch up.